prolongation costs

Also called: delay costs
HB50
costs that a principal has agreed to pay the contractor when the date for practical completion is delayed, either by a default of the principal or an agent of the principal or because of unforeseeable circumstances
In some contracts the contract documents state a specific amount to represent the prolongation costs for delays caused by the principal.